Enterprise Case Study

72-Hour Medical Facility Post-Construction Turnover

How Cleanstar National rescued a compressed timeline to secure a Certificate of Occupancy for a 100,000 sq. ft. healthcare hub in Metro Atlanta.

The Challenge: A Compressed Handover Deadline

A leading commercial developer in Metro Atlanta was facing thousands of dollars in daily liquidated damages on a new 100,000 sq. ft. outpatient medical facility. Due to supply chain delays during the framing and electrical phases, the final commissioning timeline was severely compressed.

The General Contractor (GC) had exactly 72 hours until the final architect and municipal inspectors arrived to issue the Certificate of Occupancy (CO). The facility was still covered in drywall dust, silica, and construction debris, and the newly laid VCT (Vinyl Composition Tile) flooring required full commercial floor stripping and waxing before hospital beds could be moved in. A standard cleanup crew would take two weeks. The GC called Cleanstar National.

Metric Target Outcome
Scope of Work 100,000 Sq. Ft. Medical Facility Completed in 72 Hours
Floor Commissioning Complete VCT Stripping & 4 Coats Wax Flawless Cure & Finish
Financial Impact Avoid Liquidated Damages Passed CO Inspection on 1st Walkthrough

The 72-Hour Rapid Deployment Protocol

Because Cleanstar National maintains a massive, fully W2 internal workforce, we did not have to rely on unvetted sub-contractors for this post-construction cleaning project. Within 4 hours of the GC's authorization, we dropped a 35-person OSHA-certified strike team onto the site, operating in synchronized 12-hour shifts.

Cleanstar National technicians performing commercial VCT floor stripping and waxing in an Atlanta medical facility.
Phase 3: Medical VCT Floor Commissioning
1

Hours 1-24: Rough Clean & HEPA Extraction

The day crew removed all heavy cardboard, pallets, and caulking debris. Simultaneously, technicians utilized commercial HEPA vacuums to extract fine drywall and silica dust from the ductwork registers, light fixtures, and millwork to prevent HVAC contamination.

2

Hours 25-48: Architectural Detailing

The precision detailing team washed all interior and exterior glass, sanitized the newly installed medical restrooms, polished stainless steel fixtures, and removed all factory stickers and overspray from medical casework.

3

Hours 49-65: VCT Floor Commissioning

Our IICRC-certified floor care division mobilized ride-on auto-scrubbers to chemically prep the 60,000 sq. ft. of clinical VCT flooring. Once neutralized, the team laid down four sequential layers of high-solids medical-grade floor finish, allowing precise curing times between coats.

4

Hours 66-72: The Final "Fluff"

Right before the municipal inspector arrived, a specialized 5-person crew did a final walkthrough to eradicate any residual dust that had settled overnight and eliminate footprints left by last-minute punch list contractors.

The Result: Zero Delays, Zero Damages

At exactly hour 72, the municipal inspector and head architect walked the facility. The property passed its cleanliness and safety inspections flawlessly on the very first walkthrough. The General Contractor secured the Certificate of Occupancy on time, entirely avoiding the liquidated damages clause in their contract.